Project management ch 6 | Operations Management homework help

 

 

Which of the following represents an activity on an AON project network?
  A) An arrow
  B) A line
  C) A node
  D) Both A and B are correct
  E) A, B, and C are all correct
 
 
 

Arrows on an AON project network represent:
  A) An activity
  B) Project flow
  C) Dependency
  D) Both B and C are correct
  E) Both A and B are correct
 
 
 

Which of the following is provided by a project network but not by the work breakdown structure?
  A) Dependencies
  B) Sequencing
  C) Interrelationships
  D) Both A and B are correct
  E) A, B, and C are all correct
 
 
 

Part of a project is to Develop Product Specifications. This is best classified as a(n)
  A) Event
  B) Path
  C) Activity
  D) Node
  E) Milestone
 
 
 

The critical path in a project network is the
  A) Shortest path through the network
  B) Longest path through the network
  C) Network path with the most difficult activities
  D) Network path using the most resources
  E) Network path with the most merge activities
 
 
 

An item on a project network is Design Software Completed. This is best described as a(n)
  A) Event
  B) Path
  C) Activity
  D) Node
  E) Milestone
 
 
 

A sequence of connected, dependent activities is termed a(n)
  A) Critical path
  B) Parallel path
  C) Activity chain
  D) Path
  E) Dependent chain
 
 
 

Which of the following is not one of the basic rules to follow when developing project networks?
  A) An activity cannot begin until all preceding activities have been completed
  B) Each activity must have a unique identification number
  C) Conditional statements are allowed but looping statements are not allowed
  D) An activity identification number must be larger that that of any preceding activities
  E) Networks flow from left to right
 
 
 

________ activities must be completed immediately before a particular activity.
  A) Merge
  B) Burst
  C) Predecessor
  D) Successor
  E) Critical
 
 
 
10 
The forward pass in project network calculations determines the
  A) Earliest time’s activities can begin
  B) Earliest time’s activities can be finished
  C) Duration of the project
  D) Both A and B are correct
  E) A, B, and C are all correct
 
 
 
11 
The backward pass in project network calculations determines the
  A) Latest time’s activities can begin
  B) Earliest time’s activities can be finished
  C) Critical path
  D) Both A and C are correct
  E) A, B, and C are all correct
 
 
 
12 
The amount of time an activity can be delayed and yet not delay the project is termed
  A) Total slack
  B) Free slack
  C) Critical float
  D) Float pad
  E) Slip pad
 
 
 
13 
The laying pipe example in the text illustrates the concept of
  A) Laddering
  B) Hammock activities
  C) Critical path
  D) Concurrent engineering
  E) Forward pass
 
 
 
14 
Typically an activity on a project network represents
  A) A single work package
  B) One or more tasks from a work package
  C) Several work packages
  D) A sub-deliverable
  E) A cost account
 
 
 
15 
Concurrent engineering is a good example of good use of
  A) Start to Start lags
  B) Start to Finish lags
  C) Finish to Finish lags
  D) Finish to Start lags
  E) Any of these could be correct

Order a unique copy of this paper
(550 words)

Approximate price: $22

Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

We value our customers and so we ensure that what we do is 100% original..
With us you are guaranteed of quality work done by our qualified experts.Your information and everything that you do with us is kept completely confidential.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

The Product ordered is guaranteed to be original. Orders are checked by the most advanced anti-plagiarism software in the market to assure that the Product is 100% original. The Company has a zero tolerance policy for plagiarism.

Read more

Free-revision policy

The Free Revision policy is a courtesy service that the Company provides to help ensure Customer’s total satisfaction with the completed Order. To receive free revision the Company requires that the Customer provide the request within fourteen (14) days from the first completion date and within a period of thirty (30) days for dissertations.

Read more

Privacy policy

The Company is committed to protect the privacy of the Customer and it will never resell or share any of Customer’s personal information, including credit card data, with any third party. All the online transactions are processed through the secure and reliable online payment systems.

Read more

Fair-cooperation guarantee

By placing an order with us, you agree to the service we provide. We will endear to do all that it takes to deliver a comprehensive paper as per your requirements. We also count on your cooperation to ensure that we deliver on this mandate.

Read more

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency